top of page

Bi-Weekly Update
July 21, 2023

Bi-Weekly Update
July 7, 2023

Bi-Weekly Update
June 23, 2023

Bi-Weekly Update
April 21, 2023

Bi-Weekly Update
March 31, 2023

Bi-Weekly Update
March 17, 2023

Bi-Weekly Update
February 17, 2023

Bi-Weekly Update
January 20, 2023

Bi-Weekly Update
January 6, 2023

Bi-Weekly Update
December 23, 2022

Bi-Weekly Update
December 9, 2022

Bi-Weekly Update
November 11, 2022

Bi-Weekly Update
October 27, 2022

Bi-Weekly Update
September 16, 2022

Bi-Weekly Update
September 2, 2022

Bi-Weekly Update
August 19, 2022

Bi-Weekly Update
July 22, 2022

Lots 51-53 cabinets installed. Lots 48-50 painted and cabinets delivered. Lots 45-47 trim and cabinets. Lots 42-44 trim and countertops. Lots 40-41 insulation, ground floor decks, siding. Lots 37-39 rough in, ground floor decks, inspections next week. Lots 35-36 framing punch and rough in started. Lots 33-34 framing punch. Lots 28-32 framing complete, roofing started. Lots 24-27 ground floor framing. Lots 15-23 foundations and plumbing ready, pouring slabs 7/26. Cabana framing almost completed. Prepping site for grading and remaining site work.  Scheduling final utility and irrigation installation.

Bi-Weekly Update
July 8, 2022

Trim started on lots 42-46. Mechanical units are being set on lots 42-53. Rough ins completed lots on 40-41. Rough ins being installed on lots 37-39. Decks are built on all framed units and deck boards are down. Lots 28-32 are almost done being framed. Framing on the pool house is underway! Plumbing slabs on lots 15-23 completed. Concrete scheduled for next week. Siding will start on lots 37-41 next week. Framing will start on lots 24-27 today. Cabinets are being installed in lots 51-53. Countertops being installed in lots 42 and 44 today!

Bi-Weekly Update
June 24, 2022

Pulled strings for lots 15-23. Digging footings for lots 20-23. Framing continues on lots 28-32. Porch decks, handrail posts, framing punch and rough-in inspections on lots 33-41. Drywall finishing and siding on lots 51-53. Drywall hanging, metal roofs and siding on lots 48-50. Siding, cabinets, paint, railings, metal roofs on lots 45-47. Tile, cabinets, garage doors, trim, paint and railings on lots 42-44.